We are pleased to present you with another Urban Renewal legal update which includes summaries of recent important court and tribunal decisions.
In this update we review:
- Plan TA/MK/4553 for the execution of an urban renewal project in the Ajami area in Jaffa.
- Although National Outline Plan 38 was recognized as a national interest, it is not an absolute interest and it is not an exclusive interest, and when the matter of a request to reinforce a building is being considered, other interests such as the conditions of the plot and of the area must be considered.
- A National Outline Plan 38 project in the “demolition and reconstruction” track cannot be carried out on a building which is designated for protection.
- Is the Regional Committee required to evaluate and approve permit requests in accordance with their planning potential or the built up area in practice.
Please find the full legal update here (Hebrew)